ASP MCC

I would like to say how well MCS have performed at Cropwell Bishop, following a successful FAT test we have completed the SAT sign off on site in 15 days which included 3 days E2E testing over Modbus. Having a fully operational ASP circulating flows in readiness for the SAS tanker deliveries to seed the ASP on the 24th October including interface testing to the Huber SAS thickening plant which will be commissioned in early November.

Credit where credit is due…